NAVSEA Says Attack Sub Repairs Much Improved as USS Boise Enters Yard Following 4-Year Wait

NAVSEA Says Attack Sub Repairs Much Improved as USS Boise Enters Yard Following 4-Year Wait

The Los Angeles-class attack submarine USS Boise (SSN 764) enters Souda Bay, Greece, during a scheduled port visit on Dec. 23, 2014. Boise conducted naval operations in the U.S. 6th Fleet area of responsibility in support of U.S. national security interests in Europe during its last deployment that ended in January 2015 — and the submarine has been awaiting a maintenance availability ever since, due to limited capacity in public and private yards. US Navy photo.

After years of struggling to conduct attack submarine maintenance – with the four public naval shipyards prioritizing SSN work last, behind a backlog of ballistic-missile sub and aircraft carrier work, and private shipyards finding it tough to resume submarine repair work after years of only doing new construction – the Navy appears back on track for its SSN maintenance, the head of Naval Sea Systems Command told USNI News. Read More

GAO: Navy Lost 1,891 Days of Attack Sub Operations Waiting for Repairs; Spent $1.5 Billion Supporting Idle Crews

GAO: Navy Lost 1,891 Days of Attack Sub Operations Waiting for Repairs; Spent $1.5 Billion Supporting Idle Crews

Los Angeles-class attack submarine USS Helena (SSN-725) arrives at Norfolk Naval Shipyard for a high-priority docking continuous maintenance availability on Aug. 20, 2015. US Navy Photo

Delays in maintenance have resulted in at least 1,891 lost operational days for the U.S. attack submarine fleet and cost the Navy about $1.5 billion to support boats that can’t go to sea, according to a Monday report from the Government Accountability Office. Read More

Attack Sub Maintenance at Private Yards Running Behind; NAVSEA Hopes to See Timely Delivery if More Work Given to Them

Attack Sub Maintenance at Private Yards Running Behind; NAVSEA Hopes to See Timely Delivery if More Work Given to Them

USS Greeneville (SSN-772) sits atop blocks in Dry Dock #1 at the Pearl Harbor Naval Shipyard and Intermediate Maintenance Facility, Pearl Harbor, Hawaii, on Feb. 21, 2001. The Los Angeles class attack submarine is dry-docked to assess the damage and perform necessary repairs following a Feb. 9 collision at sea with the Japanese fishing vessel Ehime Maru off the coast of Honolulu, Hawaii. DoD Photo

CAPITOL HILL – Two attack submarines sent to private shipyards for routine maintenance availabilities are running a few months behind schedule. But the Navy hopes that using these new-construction yards for sub-maintenance on a regular basis will help them become reliable providers of on-time maintenance. Read More