Tag Archives: CVN

Interview: NAVSEA 'Headed in the Right Direction' After Years of Maintenance Backlogs

Interview: NAVSEA ‘Headed in the Right Direction’ After Years of Maintenance Backlogs

Dry Dock 1 at Pearl Harbor Naval Shipyard is flooded during the undocking of the Los Angeles-class fast attack submarine USS City of Corpus Christi (SSN 705) on May 18, 2010. US Navy photo.

This post has been updated to correct which aircraft carrier is set for an upcoming docking availability.

WASHINGTON NAVY YARD — The Navy has faced massive backlogs of submarine and aircraft carrier maintenance work at its four public shipyards in recent years, at times pushing nearly ten percent of its workload into the next year.

But if 2017 was the year that bow wave of deferred maintenance caught the attention of lawmakers, it was also the year the Navy made great strides in addressing the problem – despite having a ten percent higher than average workload this year, the yards will end the year with about a quarter of the maintenance backlog they began the year with, the Naval Sea Systems Command commander Vice Adm. Tom Moore told USNI News. Read More

NAVSEA: 2,000 More Public Shipyard Workers Needed to Break Through Maintenance Backlog

NAVSEA: 2,000 More Public Shipyard Workers Needed to Break Through Maintenance Backlog

Ohio-class ballistic missile submarine USS Nebraska (SSBN 739) undocks from a dry dock at Puget Sound Navy Shipyard and Intermediate Maintenance Facility on March 8, 2016. US Navy photo.

WASHINGTON, D.C. — Despite a hiring push to increase the size of the workforce over the last several years, Naval Sea Systems Command is still short 2,000 workers in its public yards, the head of NAVSEA told lawmakers on Wednesday. Read More