Carrier Eisenhower Leaves Repair Yard to Finish Maintenance at Naval Station Norfolk

November 15, 2018 3:39 PM - Updated: November 16, 2018 1:20 PM
The aircraft carrier USS Dwight D. Eisenhower (CVN 69) transits the Elizabeth River during the ship’s transit to Norfolk Naval Shipyard in Portsmouth, Va. Dwight D. Eisenhower is preparing for a planned incremental availability at Norfolk Naval Shipyard during the maintenance phase of the Optimized Fleet Response Plan. US Navy photo.

Aircraft carrier USS Dwight D. Eisenhower (CVN-69) has departed Norfolk Naval Shipyard and is returning to Naval Station Norfolk to complete the remaining months of work on its long-overrun maintenance availability there, USNI News has learned. 

The carrier entered the maintenance yard in August 2017 and was expected to complete its planned incremental availability (PIA) by February 2018.

Instead, as USNI News previously reported, the ship’s age and demanding deployment schedule in recent years caught up with it. For the second time this decade, the carrier overshot its planned maintenance period by 10 months or more.

“This is a 41-year-old-ship and much like a vintage car, there are always things we can’t anticipate,” Ike Commanding Officer Capt. Kyle Higgins wrote in a Sept. 22 note on the ship’s Facebook page. The note has since been deleted.

Now, the Navy has made the decision to get the ship and its crew back to homeport – a decision that will not affect the timeline of the remaining repairs, but may save some money and will help the crew regain a sense of normalcy as they prepare to enter the basic phase of the Optimized Fleet Response Plan.

“The remaining PIA work does not require the ship to remain at Norfolk Naval Shipyard. The decision was made to move the ship back to Naval Station Norfolk where the crew can focus on the next phase of preparations leading to deployment,” Naval Air Force Atlantic spokesman Cmdr. Dave Hecht told USNI News in a statement this morning.
“As the PIA concludes, we are focusing on preparing our Sailors by conducting drills, attending schools, and attaining and maintaining needed qualifications through embarking on other carriers. The U.S. Navy is committed to sending to sea ships that are at a peak level of readiness in terms of manning, training and equipment. Anything less is unacceptable.”

Hull Maintenance Technician 2nd Class Lashavya Barber welds aboard the aircraft carrier USS Dwight D. Eisenhower (CVN 69) on February 15, 2018. Eisenhower is undergoing a Planned Incremental Availability (PIA) at Norfolk Naval Shipyard. US Navy photo.

The remaining PIA work will be done by both the carrier’s crew and by Norfolk Naval Shipyard personnel, who will travel from the repair yard in Portsmouth to the nearby naval station in Norfolk. Hecht said personnel routinely travel between the two locations to work on ships.

“This is a win for the ship, allowing them to somewhat get back to business, while also being a win for NNSY which will not incur any additional costs by completing testing at Naval Station Norfolk,” he said.

In another Facebook post, this one dated Sept. 13, Higgins outlined the path from wrapping up the PIA to heading out on deployment:

“We are on the path to head back to sea and as a result our workload continues to increase. We have steam plant testing, dock trials, fast cruise and sea trials on the horizon, all leading us back to Naval Station Norfolk,” he wrote.
“[W]e’re gearing up for Crew Certification, a mandatory assessment of the crew’s ability to take the ship to sea and deal with emergencies. It proves the crew can handle the basics of being underway: navigation, seamanship, safety, and damage control. From there, we’ll enter what’s known as the basic phase, where our training for combat operations begins … before we begin to integrate with the rest of the Carrier Strike Group. Each progression works toward our mission goal of being able to respond to any national security threat around the world.”

That schedule of events will still take place, but the test and certification activities will take place out of Naval Station Norfolk, whereas a carrier would usually remain in the maintenance yard until that process had been completed.

Sailors aboard the aircraft carrier USS Dwight D. Eisenhower (CVN 69) pull aboard a refueling hose on Aug. 21, 2018. Dwight D. Eisenhower is undergoing a planned incremental availability at Norfolk Naval Shipyard. US Navy photo.

It is still unclear when exactly the PIA will wrap up – the Navy has only said early 2019 – and yet to be determined when the ship will conduct its next deployment.

Also still unclear is what Ike’s delay means for other aircraft carriers. It is likely that USS George H.W. Bush (CVN-77) will be the next to go into the yard, based on the Atlantic carrier fleet’s recent deployment schedules.

Hecht told USNI News that the decision to move Ike out of the public shipyard was not due to a need to open up space for a new carrier to come in.

Megan Eckstein

Megan Eckstein

Megan Eckstein is the former deputy editor for USNI News.

Get USNI News updates delivered to your inbox