Tag Archives: RCOH

USS George Washington Begins Midlife Refueling, Overhaul With Benefit of Lessons From 5 Previous Aircraft Carriers

USS George Washington Begins Midlife Refueling, Overhaul With Benefit of Lessons From 5 Previous Aircraft Carriers

The aircraft carrier USS George Washington (CVN 73) is towed by tug boats to its new homeport in Newport News, Va., on Aug. 4, 2017. George Washington changed homeports to support the ship’s refueling and complex overhaul (RCOH) maintenance at Newport News Shipyard. US Navy photo.

Aircraft carrier USS George Washington (CVN-73) began a 48-month Refueling and Complex Overhaul at Newport News Shipbuilding earlier this month after serving for seven years as the forward-deployed carrier in Japan, creating a somewhat unique work package for the Navy’s sixth-ever RCOH. Read More

1,500 Layoffs Planned for Newport News Shipbuilding

1,500 Layoffs Planned for Newport News Shipbuilding

Thw aircraft carrier Gerald R Ford (CVN-78) and Enterprise (CVN-65) sit side by side in the South Yard as the sunrise starts to light up the sky. HII Photo

Thw aircraft carrier Gerald R Ford (CVN-78) and Enterprise (CVN-65) sit side by side in the South Yard as the sunrise starts to light up the sky. HII Photo

This post has been updated to include workforce totals at Newport News Shipbuilding.

The sole U.S. aircraft carrier builder is planning on laying off 1,500 employees over the next year-and-a-half as part of a series of cost saving measures, according to a letter sent to employees from the president of Newport News Shipbuilding this week. Read More

Navy to Build CVN-79 in 2 Phases; Ditching Plans for Early AFSB-3 Procurement

Navy to Build CVN-79 in 2 Phases; Ditching Plans for Early AFSB-3 Procurement

A unit for the future aircraft carrier John F. Kennedy (CVN-79) rests on the assembly platen at Newport News Shipbuilding on March 5, 2014. US Navy Photo

A unit for the future aircraft carrier John F. Kennedy (CVN-79) rests on the assembly platen at Newport News Shipbuilding on March 5, 2014. US Navy Photo

In their first budget hearing of the year with the House Armed Services Committee (HASC), Navy officials described their Fiscal Year 2016 plans that include speeding up construction of the aircraft carrier USS John F. Kennedy (CVN-79) without changing its delivery date, hurrying to start the USS George Washington (CVN-73) Refueling and Complex Overhaul (RCOH) planning to avoid problems down the road, and abandoning hopes of procuring a third Afloat Forward Staging Base early. Read More

Huntington Ingalls CEO ‘Concerned’ Over Delays in U.S. Navy Carrier Contracts

Huntington Ingalls CEO ‘Concerned’ Over Delays in U.S. Navy Carrier Contracts

A unit for the future aircraft carrier John F. Kennedy (CVN-79) rests on the assembly platen at Newport News Shipbuilding on March 5, 2014. US Navy Photo

A unit for the future aircraft carrier John F. Kennedy (CVN-79) rests on the assembly platen at Newport News Shipbuilding on March 5, 2014. US Navy Photo

Mike Petters — chief executive officer of Huntington Ingalls Industries (HII) — said delays in U.S. Navy contracts for the refueling and complex overhaul (RCOH) of USS George Washington (CVN-73) and construction contracts for the second Gerald Ford carrier John F. Kennedy (CVN-79) are causing the shipbuilder concern, during a Thursday call with investors. Read More