Tag Archives: Block IV

Navy Confident It Could Build 3 Virginia SSNs a Year, Though More Study Needed On Shipyard Capacity

Navy Confident It Could Build 3 Virginia SSNs a Year, Though More Study Needed On Shipyard Capacity

Attack boat Vermont (SSN-792) float-off on March 29, 2019. General Dynamics Electric Boats Photo

The Navy has “full confidence we can ramp up” to building three attack submarines per year if the Navy buildup proposed by former Defense Secretary Mark Esper were to be enacted, despite ongoing delays in Block IV Virginia-class construction, the program executive officer for submarines said today. Read More

Petters: Virginia-Class Subs Facing Most COVID-19 Delays at Newport News Shipbuilding

Petters: Virginia-Class Subs Facing Most COVID-19 Delays at Newport News Shipbuilding

Virginia-class submarine Delaware (SSN 791) was moved out of a construction facility into a floating dry dock using a transfer car system in 2018. HII Photo

Newport News Shipbuilding has seen a disproportionate amount of its COVID-19-related delays and inefficiencies hit its Virginia-class attack submarine production line, as the yard has prioritized its available workforce on supporting maintenance for in-service submarines and aircraft carriers, the company’s CEO told investors today. Read More

Navy, Sub Builders Have Recovery Plan to Get Virginia Attack Boat Deliveries Back on Schedule

Navy, Sub Builders Have Recovery Plan to Get Virginia Attack Boat Deliveries Back on Schedule

Sailors aboard to Pre-Commissioning Unit (PCU) Delaware (SSN-791) on Nov. 5, 2019. US Navy Photo

ARLINGTON, Va. – The Navy and submarine builders General Dynamics Electric Boat and Newport News Shipbuilding are executing a recovery plan to get Block IV Virginia-class submarine production back on track, after the last five submarines in Block III delivered late. Read More